Renovations at Central Middle School (Bond) |
|
|
Board Goals:
|
|
Enclosure:
|
Bid Drawings and Specifications Packages Pre-Bid Sign In Sheet Draft Contract for General Contractor Bid to Budget Bid Tab |
|
|
File Attachment:
|
|
Background & Rationale:
|
Approved Renovations at Central Middle School (Bond) |
|
|
Budget to be Charged:
|
|
Motion
|
I move the Board approve CB Construction for the renovations at Central Middle School at a base cost of $2,094,000.00 with a contingency of $209,400.00 for a total of $2,303,400.00 |
|
|
Approvals:
|
Recommended By: |
Signed By: |
|
Josh Hustad - Director of Facility Operations |
|
Signed By: |
|
Dr. Steve Shelton - Associate Superintendent of Operations |
|
Signed By: |
|
Dr. Allan Markley - Superintendent |
|
|
|
|
|
|
|