Agenda Item
Meeting Date:
12/13/2021 - 6:30 PM  
Category:
New Business  
Type:
Action  
Subject:
Renovations at Central Middle School (Bond)  
Board Goals:
 
Enclosure:
Bid Drawings and Specifications Packages
Pre-Bid Sign In Sheet
Draft Contract for General Contractor
Bid to Budget
Bid Tab
 
File Attachment:
21011.00 RCMS Rennovations & Addition CD - 100 Pct Dwgs OTB.pdf
2022 CMS Bid Tab.pdf
2022 CMS Bid to Budget 20211208.pdf
21011.00 RCMS Rennovations & Addition CD - OTB -SpecsVol1.pdf
21011.00 RCMS Rennovations & Addition CD - OTB -SpecsVol2.pdf
Pre-Bid sign-in sheet (11-29-2021).pdf
 
Background & Rationale:
Approved Renovations at Central Middle School (Bond)  
Budget to be Charged:
Bond  
Motion
I move the Board approve CB Construction for the renovations at Central Middle School at a base cost of $2,094,000.00 with a contingency of $209,400.00 for a total of $2,303,400.00  
Approvals:
Recommended By:
Signed By:
Josh Hustad - Director of Facility Operations
Signed By:  
Dr. Steve Shelton - Associate Superintendent of Operations
Signed By:  
Dr. Allan Markley - Superintendent