Agenda Item
Meeting Date:
11/7/2022 - 6:30 PM  
Category:
New Business  
Type:
Action  
Subject:
2022 HVAC Upgrades  
Board Goals:
 
Enclosure:
Estimate from Stanger Industries based off our current preferred vendor contract for Pool Pack replacements at the Wellness center as well as roof top units at Raytown High, Blueridge and Eastwood Hills.  
File Attachment:
2022 HVAC upgrades.pdf
 
Background & Rationale:
Pool Packs at the Wellness Center are past end of life and need replaced. Average life expectancy is 15 years. Current units are approx 24 years old.
Replacement of roof top units at Raytown High, Blue Ridge and Eastwood Hills that are at end of life.
 
Budget to be Charged:
Bond  
Motion
I move the board of approve Stanger Industries for the work at various locations around the district at a cost of $903,822.00 with a 10% contingency of $90,382.00 for a total not to exceed $994,204.00.  
Approvals:
Recommended By:
Signed By:
Josh Hustad - Director of Facility Operations
Signed By:  
Terry Gibson - Chief Executive Finance & Operations Officer
Signed By:  
Penelope Martin-Knox - Superintendent