Subject:
Replacement of South High School Upper Gym Floor  
Board Goals:
 
Enclosure:
Bid Tab
Contract
CB Construction Bid Proposal
 
File Attachment:
21218.00 South HS Stage Bid Tab.pdf
A101-2017 Raytown SD - CB Construction - Final 2022.03.30.pdf
A201-2017 General Conditions Raytown SD - CB Construction Final 2022.03.30.pdf
CB Construction Bid Proposal.pdf
 
Background & Rationale:
Floor has reached end of life and needs to be replaced.  
Budget to be Charged:
Capital  
Motion
I move the Board to approve CB Construction for the repair and replacement of the upper gym floor at Raytown South High School in the amount of $182,000.00 with a 10% contingency of $18,200.00 for a total of $200,200.00.  
Approvals:
Recommended By:
Signed By:
Josh Hustad - Director of Facility Operations
Signed By:  
Dr. Steve Shelton - Associate Superintendent of Operations
Signed By:  
Dr. Allan Markley - Superintendent