Review Agenda Item
Meeting Date: 5/9/2022 - 6:30 PM
Category: Report of Superintendent
Type: Info
Subject: Collapsed Sanitary Line at Raytown South Middle School
Board Goals:
Enclosure
File Attachment:
Background & Rationale: The sanitary line running under slab in the far west hallway has collapsed. It is necessary to replace. The damaged line disrupts usability to one bank of student bathrooms and three single bathrooms.
Abatement will be required of the floor tile, saw cut the floor, replace the sanitary line, patch concrete and install new floor tile.
Estimated costs-
Abatement- 9,000.00
Sanitary line repair- 40,000- 50,000.00
Replacement of VCT- 11,000.00
Replacement of sanitary line
Budget to be Charged: Capital
Motion: Information
Approvals:
Recommended By:
Signed By:
Josh Hustad - Director of Facility Operations
Signed By:
Dr. Steve Shelton - Associate Superintendent of Operations
Signed By:
Dr. Allan Markley - Superintendent