Change Order- 2021 Building Upgrades (Bond Work) |
|
|
Board Goals:
|
|
Enclosure:
|
KCMO Resolution KCMO Driveway Specs Royal Construction Change Order Hollis + Miller Proposal Request |
|
|
File Attachment:
|
|
Background & Rationale:
|
During the permit process, Stan Harris, Director of Public Works for KCMO rejected the plans that speced out asphalt entrances. The buildings currently have asphalt entrances. KCMO is requiring that all entrances be concrete. |
|
|
Budget to be Charged:
|
|
Motion
|
I move that the Board of Education approve a change order in the amount of 150,215.00 to Royal Construction and increase the overall contengency on the 2021 Building Upgrades from 135,900.00 to 211,215.00. This will leave 60,000.00 in contengency after the change order to Royal Construction for the remainder of this project. |
|
|
Approvals:
|
Recommended By: |
Signed By: |
|
Josh Hustad - Director of Facility Operations |
|
Signed By: |
|
Dr. Steve Shelton - Associate Superintendent of Operations |
|
Signed By: |
|
Dr. Allan Markley - Superintendent |
|
|
|
|
|
|
|