Epoxy Wall and Floor Coatings Removal and Replacement at Raytown South Middle School  
Board Goals:
 
Enclosure:
RFB Bid Tab Pictures of existing conditions  
File Attachment:
Epoxy Raytown South Middle School.docx.pdf
SM Epoxy Work Bid Tab.pdf
IMG_3695.jpg
IMG_3696.jpg
 
Background & Rationale:
Epoxy coated walls and floors have failed. These were done several years ago (2015) prior to UV protected technology. The natural light as well as the lights within the building has caused the walls to discolor to various shades of yellow and brown.  
Budget to be Charged:
Bond  
Motion
I move the Board approve Fine Cut for the epoxy work at Raytown South Middle School in the amount of $135,628.00 with a total not to exceed $149,190.80.  
Approvals:
Recommended By:
Signed By:
Josh Hustad - Director of Facility Operations